πΊοΈ LEGAZY-RESCUE-2025 Roadmap¶
Project: LEGAZY-RESCUE-2025 Duration: 6 weeks (74-102 hours) Status: π‘ IN PROGRESS - Phase 1
π Timeline Overview¶
Week 1: Phase 1 - Critical Infrastructure [=========> ] π΄ ACTIVE
Week 2: Phase 2 - Development Tools [ ] βͺ PENDING
Week 3: Phase 3 - AI & Automation [ ] βͺ PENDING
Week 4: Phase 4 - Utilities & Tools [ ] βͺ PENDING
Week 5: Phase 5 - Documentation & Archive [ ] βͺ PENDING
Week 6: Phase 6 - Cleanup & Verification [ ] βͺ PENDING
π΄ Phase 1: Critical Infrastructure (Week 1)¶
Goal: Migrate foundational systems that other migrations depend on Duration: 24-32 hours Status: π΄ NOT STARTED Priority: CRITICAL - Must complete before other phases
Tasks¶
| Task | Description | Time | Dependencies | Status |
|---|---|---|---|---|
| TASK-001 | PathRegistry Module | 4-6h | None | π΄ NOT STARTED |
| TASK-002 | SuperBuild System | 16-24h | TASK-001 | π΄ NOT STARTED |
| TASK-003 | Atom Generator | 6-8h | TASK-001 | π΄ NOT STARTED |
Milestones¶
- PathRegistry operational
- SuperBuild tested with real projects
- Atom generator creates valid atoms
- All Phase 1 tests passing
Success Criteria¶
- β All 3 tasks completed
- β Integration tests passing
- β Documentation updated
- β Ready for Phase 2 to begin
π‘ Phase 2: Development Tools (Week 2)¶
Goal: Migrate development and code generation tools Duration: 20-28 hours Status: βͺ PENDING Prerequisites: Phase 1 complete
Tasks¶
| Task | Description | Time | Dependencies | Status |
|---|---|---|---|---|
| TASK-004 | Plugin Workflow | 8-12h | TASK-001 | βͺ PENDING |
| TASK-005 | AudioLabUI System | 12-16h | None | βͺ PENDING |
Milestones¶
- Plugin generator creates valid plugins
- UI themes integrated
- All generators tested
- Developer documentation complete
π‘ Phase 3: AI & Automation (Week 3)¶
Goal: Integrate AI agents and automation tools Duration: 16-20 hours Status: βͺ PENDING Prerequisites: Phase 1 complete
Tasks¶
| Task | Description | Time | Dependencies | Status |
|---|---|---|---|---|
| TASK-006 | AI Agent Scripts | 8-10h | None | βͺ PENDING |
| TASK-007 | Docker Services | 8-10h | None | βͺ PENDING |
Milestones¶
- AI orchestration working
- Docker stack operational
- Integration with current tools
- Documentation complete
π’ Phase 4: Utilities & Tools (Week 4)¶
Goal: Migrate supporting tools and utilities Duration: 12-16 hours Status: βͺ PENDING Prerequisites: None (can run parallel with Phase 3)
Tasks¶
| Task | Description | Time | Dependencies | Status |
|---|---|---|---|---|
| TASK-008 | Faust Integration | 4-6h | None | βͺ PENDING |
| TASK-009 | Git Tools | 3-4h | None | βͺ PENDING |
| TASK-010 | Audit Scripts | 5-6h | None | βͺ PENDING |
Milestones¶
- All utility tools working
- Integration tested
- Documentation complete
π΅ Phase 5: Documentation & Archive (Week 5)¶
Goal: Preserve historical documentation Duration: 8-12 hours Status: βͺ PENDING Prerequisites: Phases 1-4 complete
Tasks¶
| Task | Description | Time | Dependencies | Status |
|---|---|---|---|---|
| TASK-011 | Historical Docs | 4-6h | None | βͺ PENDING |
| TASK-012 | Architecture Docs | 4-6h | None | βͺ PENDING |
Milestones¶
- All docs organized
- Archive structure created
- Index and cross-references complete
βͺ Phase 6: Cleanup & Verification (Week 6)¶
Goal: Clean up and finalize project Duration: 4-6 hours Status: βͺ PENDING Prerequisites: All previous phases complete
Tasks¶
| Task | Description | Time | Dependencies | Status |
|---|---|---|---|---|
| TASK-013 | Delete Obsolete | 2-3h | All tasks | βͺ PENDING |
| TASK-014 | Final Verification | 2-3h | TASK-013 | βͺ PENDING |
Milestones¶
- All obsolete files deleted
- No broken references
- Legacy archived
- Project closed
π Progress Metrics¶
Overall Progress¶
Phases Complete: 0 / 6 (0%)
Tasks Complete: 0 / 14 (0%)
Hours Spent: 0 / 74-102
Critical Items: 0 / 3 (0%)
High Priority: 0 / 4 (0%)
Current Week Focus¶
Week 1: Complete TASK-001, TASK-002, TASK-003
π― Key Milestones¶
Milestone 1: Foundation Ready (End Week 1)¶
- β PathRegistry working
- β SuperBuild operational
- β Atom generation functional Status: π΄ NOT REACHED
Milestone 2: Tools Complete (End Week 2)¶
- β All generators working
- β UI system integrated Status: βͺ PENDING
Milestone 3: Infrastructure Complete (End Week 3)¶
- β AI integration done
- β Docker services ready Status: βͺ PENDING
Milestone 4: Migration Complete (End Week 4)¶
- β All utilities migrated
- β All high-value assets rescued Status: βͺ PENDING
Milestone 5: Documentation Complete (End Week 5)¶
- β Historical records archived
- β All documentation updated Status: βͺ PENDING
Milestone 6: Project Complete (End Week 6)¶
- β Legacy cleaned up
- β Final verification passed
- β Project closed Status: βͺ PENDING
β οΈ Critical Path¶
The critical path for this project:
TASK-001 (PathRegistry)
β
TASK-002 (SuperBuild) βββ End of Week 1
β
TASK-003 (Atom Generator)
β
TASK-004 (Plugin Workflow) βββ End of Week 2
β
[Parallel: TASK-005, TASK-006, TASK-007]
β
[Parallel: TASK-008, TASK-009, TASK-010]
β
[Parallel: TASK-011, TASK-012]
β
TASK-013 (Cleanup)
β
TASK-014 (Verification) βββ PROJECT COMPLETE
Critical Tasks (on critical path): - TASK-001, TASK-002, TASK-003, TASK-004, TASK-013, TASK-014
Parallel Tasks (can overlap): - TASK-005 through TASK-012
π¨ Risk Management¶
High Risk Items¶
- SuperBuild Complexity (TASK-002)
- Risk: 2,847 lines of complex code
-
Mitigation: Allocate extra time, thorough testing
-
Path Dependencies
- Risk: Hardcoded paths throughout legacy code
-
Mitigation: PathRegistry first (TASK-001)
-
Integration Issues
- Risk: Legacy tools may not work with current system
- Mitigation: Incremental testing, rollback plans
Medium Risk Items¶
- Time Estimation
- Risk: Complex tasks may take longer
-
Mitigation: Built-in buffer (74-102h range)
-
Documentation Gaps
- Risk: Legacy code may be undocumented
- Mitigation: Code analysis, testing, reverse engineering
π Key Dates¶
| Date | Event | Status |
|---|---|---|
| 2025-10-17 | Project Created | β DONE |
| 2025-10-24 | Phase 1 Target Complete | π΄ PENDING |
| 2025-10-31 | Phase 2 Target Complete | βͺ PENDING |
| 2025-11-07 | Phase 3 Target Complete | βͺ PENDING |
| 2025-11-14 | Phase 4 Target Complete | βͺ PENDING |
| 2025-11-21 | Phase 5 Target Complete | βͺ PENDING |
| 2025-11-30 | Project Target Complete | βͺ PENDING |
π Iteration Strategy¶
Weekly Reviews¶
Every Monday: - Review previous week progress - Adjust estimates if needed - Re-prioritize tasks if needed - Update roadmap
Daily Updates¶
Update PROGRESS.md with: - Tasks started/completed - Hours spent - Blockers encountered - Next steps
π Escalation Path¶
Blockers¶
- Document in task file
- Update PROGRESS.md
- Escalate if blocking >4 hours
Scope Changes¶
- Discuss in project review
- Update roadmap
- Document decision
Roadmap Status: π‘ ACTIVE Last Updated: 2025-10-17 Next Review: 2025-10-24 (End of Week 1)